Wynn Al Marjan Island, Ras Al Khaimah: opening date, gaming licence and every update
Last checked 23 November 2026 · Inside RAK Desk · اقرأ بالعربية
Wynn Al Marjan Island is an integrated resort with a hotel tower, restaurants, a theatre and a licensed gaming area under construction on Al Marjan Island in Ras Al Khaimah, United Arab Emirates. Wynn Resorts said in its results of 5 November 2026 that the resort is expected to open in September 2027, after earlier guidance of the first quarter of 2027. It is being built by a joint venture of affiliates of Wynn Resorts, Marjan and RAK Hospitality Holding, in which Wynn holds 40%.
Wynn Al Marjan Island at a glance
Each line gives the figure, who said it and when. Where sources differ, all versions are shown.
| Opening date (latest) | September 2027Wynn's wording in its 5 Nov 2026 results: "currently expected to open in September 2027". First given in its 4 Aug 2026 results. See the timeline for earlier guidance.Source: Wynn Resorts (SEC Form 8-K, Exhibit 99.1), 5 Nov 2026; Wynn Resorts (SEC Form 8-K, Exhibit 99.1), 4 Aug 2026 |
|---|---|
| Operator | Wynn Resorts (Nasdaq: WYNN)Wynn's 2025 annual report says it announced plans with its partners in January 2022 for the development and management of the resort.Source: Wynn Resorts (SEC Form 10-K), 2 Mar 2026 |
| Owner and partners | Island 3 AMI FZ-LLC, a joint venture of affiliates of Wynn Resorts, Marjan and RAK Hospitality HoldingWynn holds a 40% equity interest (10-Q, 5 Nov 2026). The partners are named in Wynn's licence announcement of 4 Oct 2024. InsideRAK has not seen a published split of the other 60%.Source: Wynn Resorts, 4 Oct 2024; Wynn Resorts (SEC Form 10-Q), 5 Nov 2026 |
| Location | Al Marjan Island, Ras Al Khaimah, UAEWynn describes a 60-hectare island site less than 50 miles from Dubai International Airport (official site, checked 23 Nov 2026).Source: Wynn Al Marjan Island (official site), checked 23 Nov 2026 |
| Rooms | About 1,500 to 1,542 (figures differ)1,542 rooms (Wynn, 4 Oct 2024); "over 1,500-room hotel" (Wynn 10-K, 2 Mar 2026); 1,530 accommodations including 313 at Enclave (Marjan, checked 23 Nov 2026).Source: Wynn Resorts, 4 Oct 2024; Wynn Resorts (SEC Form 10-K), 2 Mar 2026; Marjan, checked 23 Nov 2026 |
| Gaming licence | Licensed by the UAE's General Commercial Gaming Regulatory Authority (GCGRA)Wynn announced on 4 Oct 2024 that the GCGRA had issued a Commercial Gaming Facility Operator licence to the developing entity. The GCGRA's licensee list names Island 3 AMI FZ-LLC (DBA: Wynn Al Marjan) as its land-based gaming facilities licensee (checked 23 Nov 2026).Source: Wynn Resorts, 4 Oct 2024; General Commercial Gaming Regulatory Authority, checked 23 Nov 2026 |
| Investment | US$5.7 billion, as stated by MarjanMarjan's project page gives US$5.7 billion total investment (checked 23 Nov 2026). Wynn's releases and 10-Q do not state a total; they report Wynn's 40% share: $1.12 billion contributed to 30 Sep 2026 and $465m to $590m still to come, both covering Janu Al Marjan Island as well. A delayed-draw term loan facility of about $2.4 billion was signed in February 2025.Source: Marjan, checked 23 Nov 2026; Wynn Resorts (SEC Form 10-Q), 5 Nov 2026 |
| Gaming area | 225,000 sq ftWynn 2025 annual report (Form 10-K).Source: Wynn Resorts (SEC Form 10-K), 2 Mar 2026 |
What will be there
As described by Wynn Resorts and Marjan before opening. Plans can change before a resort opens.
The tower
A 70-storey resort tower that Wynn says rises 352 metres above the sea including its spire. Wynn reported the tower topped out in the fourth quarter of 2025.
Source: Wynn Al Marjan Island (official site), checked 23 Nov 2026; Wynn Resorts (SEC Form 8-K, Exhibit 99.1), 12 Feb 2026Rooms and Enclave
Between about 1,500 and 1,542 rooms depending on the source and date (see the facts table). Marjan lists 313 suites and residences in Enclave, a hotel-within-the-hotel on the upper floors.
Source: Wynn Resorts, 4 Oct 2024; Wynn Resorts (SEC Form 10-K), 2 Mar 2026; Marjan, checked 23 Nov 2026Dining
22 restaurants, bars and lounges, plus a beach club, according to Wynn's site and Marjan.
Source: Wynn Al Marjan Island (official site), checked 23 Nov 2026; Marjan, checked 23 Nov 2026Theatre
The Wynn Theater, where Wynn says an original production created with Punchdrunk will run. Wynn's site gives capacity as 450 seated upstairs, 48 downstairs and 402 roaming guests.
Source: Wynn Al Marjan Island (official site), checked 23 Nov 2026Events centre
The Coral Court events and celebrations centre, given as 7,708 square metres with a 2,633-square-metre ballroom on Wynn's current site. Wynn's 2024 announcement gave 7,500 square metres, and Marjan's home page gives 145,000 sq ft.
Source: Wynn Al Marjan Island (official site), checked 23 Nov 2026; Wynn Resorts, 4 Oct 2024; Marjan, checked 23 Nov 2026Beach, pools and marina
A private white-sand beach, pools with cabanas, a kids' club and a full-service marina. Wynn's own site gives the beach as 420 metres in one place and 550 metres in another.
Source: Wynn Al Marjan Island (official site), checked 23 Nov 2026Gaming area
A licensed gaming area of 225,000 square feet, per Wynn's 2025 annual report. Marjan describes it as the region's first land-based gaming facility.
Source: Wynn Resorts (SEC Form 10-K), 2 Mar 2026; Marjan, checked 23 Nov 2026Janu Al Marjan Island next door
A separate Aman Group hotel and residential project by the same joint venture, with a 132-room hotel. Wynn's 10-K (March 2026) said late 2028; its 10-Q of 5 November 2026 says 2029.
Source: Wynn Resorts (SEC Form 10-K), 2 Mar 2026; Wynn Resorts (SEC Form 10-Q), 5 Nov 2026The gaming licence
The General Commercial Gaming Regulatory Authority (GCGRA) is a federal UAE authority, headquartered in Abu Dhabi. It says it holds exclusive jurisdiction to regulate, license and supervise commercial gaming activities and facilities in the UAE. Its own press release dates its establishment to 3 September 2023.
On 4 October 2024 Wynn Resorts announced that the GCGRA had issued a Commercial Gaming Facility Operator licence to the entity developing Wynn Al Marjan Island, the joint venture with Marjan and RAK Hospitality Holding. Wynn described it as the first commercial gaming facility licence in the UAE. The GCGRA's first licensee overall was The Game LLC, licensed on 28 July 2024 to run the UAE Lottery, a different licence category.
As of 23 November 2026 the GCGRA's public licensee list shows one land-based gaming facilities licensee: Island 3 AMI FZ-LLC, trading as Wynn Al Marjan. The GCGRA states that offering or facilitating commercial gaming in the UAE without its licence is illegal.
This page covers the licence as a regulatory and economic story. It does not link to gambling services or carry odds, offers or betting content.
Sources: General Commercial Gaming Regulatory Authority, checked 23 Nov 2026; General Commercial Gaming Regulatory Authority, 3 Sep 2023; General Commercial Gaming Regulatory Authority, 28 Jul 2024; Wynn Resorts, 4 Oct 2024; General Commercial Gaming Regulatory Authority, checked 23 Nov 2026
Timeline of announcements
- January 2022 Wynn Resorts, Island 3 and Marjan. Plans announced for the development and management of Wynn Al Marjan Island, as recounted in Wynn's 2025 annual report.Source: Wynn Resorts (SEC Form 10-K), 2 Mar 2026
- 3 Sep 2023 GCGRA. The UAE's federal commercial gaming regulator is established.Source: General Commercial Gaming Regulatory Authority, 3 Sep 2023
- 28 Jul 2024 GCGRA. Licenses The Game LLC to run the UAE Lottery, which it calls its first licensee.Source: General Commercial Gaming Regulatory Authority, 28 Jul 2024
- 4 Oct 2024 Wynn Resorts. Announces that the GCGRA issued a Commercial Gaming Facility Operator licence to the resort's developer.Source: Wynn Resorts, 4 Oct 2024
- February 2025 Wynn Al Marjan Island FZ-LLC. Signs a delayed-draw secured term loan facility of about $2.4 billion with a group of lenders to finance construction, per Wynn's 10-Q.Source: Wynn Resorts (SEC Form 10-Q), 5 Nov 2026
- 6 Nov 2025 Wynn Resorts. Says concrete is being poured for the last few floors of the 70-storey tower; opening expected in 2027.Source: Wynn Resorts (SEC Form 8-K, Exhibit 99.1), 6 Nov 2025
- 12 Feb 2026 Wynn Resorts. Reports the tower topped out in the fourth quarter of 2025; opening expected in the first quarter of 2027.Source: Wynn Resorts (SEC Form 8-K, Exhibit 99.1), 12 Feb 2026
- 11 Mar 2026 Wynn Resorts. Issues an update during the regional conflict: construction has resumed after a short pause.Source: Wynn Resorts (SEC Form 8-K, Exhibit 99.1), 11 Mar 2026
- 7 May 2026 Wynn Resorts. Results give the opening as 2027, dropping the first-quarter timing. On the earnings call, as reported by The National on 9 May, chief executive Craig Billings said Wynn expected a "modest delay" and would quantify it later.Source: Wynn Resorts (SEC Form 8-K, Exhibit 99.1), 7 May 2026; The National, 9 May 2026
- 4 Aug 2026 Wynn Resorts. Sets the opening for September 2027. The National reported on 5 August that Wynn said on the call the project's cost rose by $600 million to about $5.7 billion.Source: Wynn Resorts (SEC Form 8-K, Exhibit 99.1), 4 Aug 2026; The National, 5 Aug 2026
- 5 Nov 2026 Wynn Resorts. Keeps September 2027 and says interior fit-out of all guest rooms is under way.Source: Wynn Resorts (SEC Form 8-K, Exhibit 99.1), 5 Nov 2026
Where the sources differ
We have not picked one version where official and reported figures disagree. Here is what each source said, and when.
Wynn's guidance moved from "2027" (6 Nov 2025) to "the first quarter of 2027" (12 Feb 2026), back to "2027" (7 May 2026) and to "September 2027" (4 Aug and 5 Nov 2026). The National described the earlier target as spring 2027 on 9 May 2026, but on 5 Aug 2026 wrote that the opening had been pushed back from a 2026 target. Wynn's own releases did not say 2026 at any point we checked, so this page uses Wynn's wording.
1,542 rooms (Wynn, 4 Oct 2024); an "over 1,500-room hotel" (Wynn 10-K, 2 Mar 2026); 1,530 accommodations (Marjan, checked 23 Nov 2026, and The National, 5 Aug 2026).
The National reported $5.1 billion on 9 May 2026 and about $5.7 billion on 5 Aug 2026, after Wynn's call. Marjan's page gives US$5.7 billion. Wynn's releases and 10-Q report only its own 40% share, and those figures also cover the neighbouring Janu Al Marjan Island project.
About 9,000 direct jobs, per The National's 5 Aug 2026 report (corrected on 6 Aug from 3,000). Marjan's page says more than 7,000 direct jobs are expected.
Wynn's site gives 352 metres above the sea including the spire. The National gave 305 metres on 9 May 2026. Both say 70 storeys.
Wynn's own site gives the private beach as 420 metres in one section and 550 metres in its FAQ. The events centre was 7,500 square metres in Wynn's 2024 announcement and is 7,708 square metres on Wynn's site and Marjan's Wynn page, while Marjan's home page gives a 145,000 sq ft (about 13,500 square metres) meetings and events centre (all checked 23 Nov 2026).
Wynn's 10-K (2 Mar 2026) said the neighbouring Aman project would open in late 2028. Its 10-Q of 5 Nov 2026 says 2029.
Jobs and recruitment
Recruitment runs through the careers page on the official Wynn Al Marjan Island site. When we checked it on 23 November 2026 it showed job categories including rooms, food and beverage, gaming, facilities, entertainment and security; the same page also links to careers at Wynn's other resorts.
The National reported on 5 August 2026 that 425 people then worked for Wynn Al Marjan Island and that about 9,000 would be needed before launch. Marjan's project page puts expected direct jobs at more than 7,000.
This page links only to the official careers site, not to third-party job listings.
Sources: Wynn Al Marjan Island (official site), checked 23 Nov 2026; The National, 5 Aug 2026; Marjan, checked 23 Nov 2026
What it means for Al Marjan Island
Wynn Al Marjan Island is the largest of the four Al Marjan Island hotel projects InsideRAK's directory lists for 2027, alongside JW Marriott, Address Beach Resort and Nobu. Our Al Marjan Island guide lists the resorts open today and the 2027 openings.
The same joint venture is building Janu Al Marjan Island next door with Aman Group, a 132-room hotel with residences that Wynn now expects in 2029.
For how the 2027 openings affect hotel supply across the emirate, see our analysis The 2027 problem: RAK's hotel supply is arriving all at once and the hotels directory. Claims about the resort's effect on room rates or property prices are forecasts, not measured results.
Every InsideRAK story on Wynn Al Marjan Island (18)
Newest first. This list updates automatically when we publish a new story with Wynn in the headline. Each story lists its own sources.
- 9 Nov 2026 Beyond Wynn: The Hotel Pipeline Shaping Ras Al Khaimah’s Next Chapter Hotels
- 29 Oct 2026 Wynn Al Marjan Drives Property Surge as Al Hamra CEO Stresses Legacy Properties & Real Estate
- 25 Oct 2026 Wynn Al Marjan build advances as RAK mission visits four US states Gaming & iGaming
- 20 Oct 2026 Wolfe Research Sees Wynn Al Marjan Exceeding $1.66bn Annual Gaming Revenue Gaming & iGaming
- 18 Oct 2026 Ras Al Khaimah Hotels Renovate to Capture the ‘Wynn Effect’ Hotels
- 18 Oct 2026 UAE Officials Tour Nevada as Wynn Project Advances Gaming & iGaming
- 11 Oct 2026 Wynn Al Marjan Unveils 98-Berth Superyacht Marina for 2027 Integrated Resort Gaming & iGaming
- 27 Sep 2026 Wynn Recruitment Signals Casino Infrastructure Progress Ahead of UAE Opening Gaming & iGaming
- 21 Sep 2026 Wynn Al Marjan Island Unveils Two 7-Bedroom Royal Apartments Property
- 25 Aug 2026 Wynn Al Marjan Island unveils luxury townhomes up to 1,110 sqm Property
- 11 Aug 2026 Wynn Al Marjan Island reveals its 550-metre beachfront Hotels
- 5 Aug 2026 Wynn Al Marjan Island sets a September 2027 opening as costs rise to $5.7 billion Hotels
- 19 Jul 2026 Wynn Al Marjan Island names India a priority market Tourism
- 18 Jul 2026 PHD MENA named media agency of record for Wynn Al Marjan Island Markets
- 16 Jul 2026 Wynn Al Marjan Island partners with Punchdrunk on an original theatre production Tourism
- 16 Jul 2026 Wynn UAE appoints a VP of Private Access Tourism
- 15 Jul 2026 Wynn Al Marjan Island enters its final construction phase Tourism
- 9 May 2026 Wynn Al Marjan Island opening delayed by the Iran war Tourism
Frequently asked questions
When does Wynn Al Marjan Island open?
Wynn Resorts says Wynn Al Marjan Island is expected to open in September 2027. It first gave that month in its results of 4 August 2026 and repeated it on 5 November 2026. Earlier guidance was the first quarter of 2027 (February 2026); in May 2026 Wynn said only 2027 and warned of a modest delay.
Source: Wynn Resorts (SEC Form 8-K, Exhibit 99.1), 5 Nov 2026; Wynn Resorts (SEC Form 8-K, Exhibit 99.1), 4 Aug 2026; Wynn Resorts (SEC Form 8-K, Exhibit 99.1), 12 Feb 2026; Wynn Resorts (SEC Form 8-K, Exhibit 99.1), 7 May 2026; The National, 9 May 2026Where is Wynn Al Marjan Island?
Wynn Al Marjan Island is on Al Marjan Island, a man-made archipelago off the coast of Ras Al Khaimah in the United Arab Emirates. Wynn describes the resort site as a 60-hectare island less than 50 miles from Dubai International Airport, overlooking the Arabian Gulf.
Source: Wynn Al Marjan Island (official site), checked 23 Nov 2026Does Wynn Al Marjan Island have a gaming licence?
Yes. Wynn announced on 4 October 2024 that the UAE's General Commercial Gaming Regulatory Authority had issued a Commercial Gaming Facility Operator licence to the joint venture developing the resort. The regulator's public licensee list names Island 3 AMI FZ-LLC, trading as Wynn Al Marjan, as its land-based gaming facilities licensee.
Source: Wynn Resorts, 4 Oct 2024; General Commercial Gaming Regulatory Authority, checked 23 Nov 2026Who owns Wynn Al Marjan Island?
The resort is being developed by Island 3 AMI FZ-LLC, a joint venture between affiliates of Wynn Resorts, Marjan and RAK Hospitality Holding. Wynn Resorts holds a 40% equity interest, according to its quarterly filing of 5 November 2026. InsideRAK has not seen a published breakdown of how the remaining 60% is held.
Source: Wynn Resorts, 4 Oct 2024; Wynn Resorts (SEC Form 10-Q), 5 Nov 2026How many rooms will Wynn Al Marjan Island have?
Figures differ by source and date. Wynn's 2024 licence announcement said 1,542 rooms, its March 2026 annual report says an over 1,500-room hotel, and Marjan's project page lists 1,530 accommodations, including 313 suites and residences in the Enclave section on the upper floors.
Source: Wynn Resorts, 4 Oct 2024; Wynn Resorts (SEC Form 10-K), 2 Mar 2026; Marjan, checked 23 Nov 2026How much does Wynn Al Marjan Island cost?
Marjan's project page puts the total investment at US$5.7 billion. The National reported in August 2026 that Wynn said costs had risen by $600 million to about that level. Wynn's own filings give only its 40% share: $1.12 billion contributed by 30 September 2026, with $465 million to $590 million still to come. Both figures also cover the neighbouring Janu Al Marjan Island.
Source: Marjan, checked 23 Nov 2026; The National, 5 Aug 2026; Wynn Resorts (SEC Form 10-Q), 5 Nov 2026Sources
Every source below was opened by InsideRAK on 23 November 2026. Reports from other publishers are cited where they are the only record of a statement, such as remarks on an earnings call, and are summarised in our own words.
- Wynn Resorts Announces Receipt of Gaming Operator License for Wynn Al Marjan Island · Wynn Resorts, 4 Oct 2024.
- Wynn Resorts, Limited Reports Third Quarter 2025 Results · Wynn Resorts (SEC Form 8-K, Exhibit 99.1), 6 Nov 2025.
- Wynn Resorts, Limited Reports Fourth Quarter and Year End 2025 Results · Wynn Resorts (SEC Form 8-K, Exhibit 99.1), 12 Feb 2026.
- Annual report for the year ended 31 December 2025 · Wynn Resorts (SEC Form 10-K), 2 Mar 2026.
- Wynn Resorts Issues Update on Wynn Al Marjan Island · Wynn Resorts (SEC Form 8-K, Exhibit 99.1), 11 Mar 2026.
- Wynn Resorts, Limited Reports First Quarter 2026 Results · Wynn Resorts (SEC Form 8-K, Exhibit 99.1), 7 May 2026.
- Wynn Resorts, Limited Reports Second Quarter 2026 Results · Wynn Resorts (SEC Form 8-K, Exhibit 99.1), 4 Aug 2026.
- Wynn Resorts, Limited Reports Third Quarter 2026 Results · Wynn Resorts (SEC Form 8-K, Exhibit 99.1), 5 Nov 2026.
- Quarterly report for the period ended 30 September 2026 · Wynn Resorts (SEC Form 10-Q), 5 Nov 2026.
- GCGRA home page · General Commercial Gaming Regulatory Authority, checked 23 Nov 2026.
- Our Licensees · General Commercial Gaming Regulatory Authority, checked 23 Nov 2026.
- Press Release - Commercial Gaming Regulator Established in UAE · General Commercial Gaming Regulatory Authority, 3 Sep 2023.
- Press Release - The GCGRA awards License for UAE Lottery · General Commercial Gaming Regulatory Authority, 28 Jul 2024.
- Wynn Al Marjan Island · Marjan, checked 23 Nov 2026.
- Marjan home page · Marjan, checked 23 Nov 2026.
- Wynn Al Marjan Island home page and FAQ · Wynn Al Marjan Island (official site), checked 23 Nov 2026.
- Careers · Wynn Al Marjan Island (official site), checked 23 Nov 2026.
- Opening of Ras Al Khaimah's landmark Wynn gaming resort delayed by Iran war · The National, 9 May 2026. Cited in our story.
- Wynn sets new opening date for UAE resort and raises costs by $600 million (updated 6 August 2026) · The National, 5 Aug 2026. Cited in our story.
Spot something out of date? corrections@insiderak.com